Ex Equipment Technical Bid Evaluation Checklist: A 25-Point TBE Review

25-point Ex equipment TBE checklist to evaluate certification, hazardous area suitability, technical compliance, deviations, and documentation

Technical Bid Evaluation (TBE): checking Ex equipment against project requirements, certification, hazardous area classification, and technical compliance.

Technical bid evaluation is one of the most important stages in the procurement of electrical equipment for hazardous areas. A vendor offer may appear compliant at first glance, but important differences can exist in certification, hazardous area suitability, temperature class, equipment protection level, ambient temperature, cable entries, accessories, and documentation.

A structured Technical Bid Evaluation (TBE) helps the engineering and procurement team compare the vendor offer against the actual project requirements instead of evaluating equipment only by model number, price, or general Ex certification.

This article provides a practical 25-point checklist for evaluating Ex electrical equipment before commercial evaluation and purchase order placement.

Engineering note: This checklist is a practical evaluation framework, not a substitute for project requirements. Use the applicable project specifications, hazardous area classification documents, equipment datasheets, certification documents, standards, and installation requirements as the controlling references.

What Should a Technical Bid Evaluation Check?

The purpose of a TBE is not simply to determine whether a product is Ex certified. The evaluation should establish whether the exact equipment and configuration offered satisfy the complete technical requirements.

IEC 60079-14 addresses electrical installation design, equipment selection and installation, initial inspection, documentation, and personnel competency within its scope. A TBE supports this process by connecting the project requirements with the offered equipment, certification, configuration, and installation requirements.

25-Point Ex Equipment TBE Checklist

Use the following checklist to compare the vendor's offer against the RFQ, project datasheet, equipment schedule, and applicable project specifications.

# Check Item What to Verify
1Equipment TypeConfirm that the offered equipment performs the function required by the RFQ, datasheet, or equipment schedule.
2Manufacturer and ModelRecord the exact manufacturer, product family, model number, and configuration offered.
3Hazardous Area ClassificationCheck suitability for the applicable Zone or other hazardous area classification specified for the installation.
4Equipment Protection Level (EPL)Verify that the offered EPL is suitable for the required hazardous area and application.
5Ex Protection TypeConfirm the required protection concept, such as Ex d, Ex e, Ex i, Ex p, Ex ec, Ex t, or another applicable type.
6Gas or Dust GroupVerify the applicable gas group or dust group against the hazardous substance and project requirements.
7Temperature ClassCheck that the temperature class or maximum surface temperature meets the project requirements and hazardous substance limitations.
8Ambient TemperatureCompare the certified or specified ambient temperature range with the actual project environmental requirements.
9Ingress ProtectionVerify the IP rating against the environmental and installation requirements.
10Electrical RatingCheck voltage, frequency, current, power, phase, and other applicable electrical characteristics.
11Performance RequirementsVerify application-specific performance, such as lumen output, operating capacity, communication capability, or load rating.
12Material of ConstructionCheck the enclosure, body, lens, gasket, mounting material, and other materials against environmental and project requirements.
13Cable EntriesVerify entry type, thread size, quantity, material, certification requirements, and compatibility with the installation.
14Cable GlandsConfirm whether glands are included and whether their type, certification, and specification suit the equipment and cable construction.
15Plugs and AccessoriesCheck blanking plugs, reducers, adaptors, brackets, mounting hardware, guards, visors, and other required accessories.
16Ex CertificateVerify the applicable certificate and confirm that it corresponds to the equipment type and protection concept offered.
17Certificate ConditionsReview special conditions of use, limitations, certificate suffixes, variants, and associated documentation where applicable.
18Ex MarkingCompare the marking against the required equipment group, protection type, gas or dust group, temperature class, and EPL.
19Product ConfigurationConfirm that the certified configuration corresponds to the actual offer, including options and accessories where relevant.
20Vendor DatasheetCompare the vendor datasheet line by line with the project datasheet and RFQ requirements.
21Technical DeviationsIdentify and record every deviation. Do not assume that an unmentioned requirement is compliant.
22Installation RequirementsCheck mounting orientation, cable entry arrangement, earthing, clearances, environmental conditions, and other installation constraints.
23DocumentationConfirm the availability of datasheets, certificates, manuals, drawings, schedules, declarations, and other required documents.
24Inspection and TestingIdentify required inspections, tests, certificates, routine test records, and project-specific documentation before shipment or installation.
25Final Compliance StatusAssign a clear status—Comply, Deviation, Clarification Required, or Not Comply—based on documented evidence.

Do Not Evaluate the Offer From the Ex Certificate Alone

One common evaluation error is treating the existence of an IECEx or other Ex certificate as proof that the complete vendor offer satisfies the project requirements.

Certification is essential where required, but it does not eliminate the need to check the exact model, configuration, environmental limits, electrical ratings, performance, cable entries, accessories, and installation requirements.

For example, a certificate may cover a particular protection concept and temperature class, while the project also requires an ambient temperature range of -40°C to +60°C, a specific cable entry arrangement, or a minimum lighting output. These requirements must be assessed separately.

A Practical TBE Comparison Matrix

Place the project requirement and vendor offer side by side. Record the supporting document and explain any difference instead of relying on a general statement of compliance.

Requirement Project Requirement Vendor Offer Status Remarks
Hazardous AreaZone 1Zone 1ComplyConfirm from applicable technical documents.
Gas GroupIICIICComplyCheck against the applicable certificate and marking.
EPLGbGbComplyConfirm that the protection level is suitable for the application.
Temperature ClassT4T4ComplyVerify the actual offered configuration.
Ambient Temperature-40°C to +60°C-20°C to +60°CDeviationVendor clarification or a suitable alternative is required.
Ingress ProtectionIP66IP66ComplyConfirm from product documentation.
Cable EntrySpecified arrangementAlternative proposedClarification RequiredCheck compatibility, installation requirements, and certification conditions.

The entries above are illustrative examples, not approval of any specific equipment.

Why Vendor Deviations Should Be Recorded Clearly

A technical deviation should not disappear inside a vendor quotation. Recording it in the TBE creates a traceable record of what was offered, what differs from the project requirements, and what remains unresolved.

For example:

Vendor proposes an ambient temperature range of -20°C to +60°C against the project requirement of -40°C to +60°C. Vendor to confirm suitability for the specified operating conditions or propose an alternative configuration with supporting technical documentation.

This makes the technical gap visible to engineering, procurement, and the vendor before the commercial decision is finalized.

Comply, Deviation, Clarification Required, or Not Comply?

  • Comply: The documented offer satisfies the stated requirement.
  • Deviation: The documented offer differs from the stated requirement. The deviation must be recorded and assessed.
  • Clarification Required: The available information is insufficient to establish compliance.
  • Not Comply: The documented offer fails a mandatory technical requirement, subject to the project's evaluation procedure.

Use the project's approved TBE procedure for handling deviations, mandatory requirements, and technical clarifications. Do not mark an item as compliant simply because the vendor has not identified a deviation.

Five Documents to Cross-Check During TBE

A sound evaluation should cross-check relevant information across multiple documents rather than relying on a single vendor submission.

  1. Project datasheet or equipment specification
  2. Vendor technical datasheet
  3. Ex certificate and associated certification documentation
  4. Vendor technical offer and deviation list
  5. Installation requirements and project drawings, where applicable

Look for inconsistencies between these documents. The model number in the quotation should correspond with the datasheet and certified equipment configuration. Separately quoted accessories should also be checked against the required configuration and installation arrangement.

Example: How One Small Deviation Can Affect the Evaluation

Consider an illustrative outdoor Ex luminaire requirement:

  • Hazardous area: Zone 1
  • Gas group: IIC
  • EPL: Gb
  • Temperature class: T4
  • Ambient temperature: -40°C to +60°C
  • Minimum light output: 12,000 lm
  • Ingress protection: IP66
  • Electrical supply: 230 V AC, 50 Hz

Assume a vendor proposes a luminaire meeting the stated Zone, gas group, EPL, temperature class, IP rating, voltage, and light output requirements, but its documented ambient range is only -20°C to +60°C.

The offer should not be marked fully compliant just because the equipment has the correct Ex certification. The ambient temperature requirement is a separate criterion. Record the difference as a deviation or clarification item until the proposed configuration's suitability is established.

TBE Review Sequence

  1. Read the RFQ, project datasheet, and applicable specifications.
  2. Identify the hazardous area classification and required equipment suitability.
  3. Check EPL, protection type, gas or dust group, and temperature requirements.
  4. Confirm the exact manufacturer, model, and offered configuration.
  5. Review the applicable Ex certificate and its conditions.
  6. Compare electrical ratings, environmental limits, and performance.
  7. Review cable entries, glands, accessories, and installation requirements.
  8. Cross-check the supporting documents.
  9. Record deviations and request clarification where evidence is incomplete.
  10. Finalize the TBE with a traceable status and supporting remarks for each requirement.

What a Good TBE Should Leave Behind

The final TBE should allow another engineer to understand why an offer was considered compliant, which deviations were identified, what clarifications were obtained, and which items remain unresolved.

A well-documented TBE becomes part of the project's technical decision record. It supports procurement decisions and provides a reference for subsequent document review, inspection, and installation activities.

Related Reading

References

  • IEC 60079-14:2024 — Explosive atmospheres — Part 14: Electrical installation design, selection and installation of equipment, including initial inspection.
  • IEC 60079 series — Explosive atmospheres.